Analytics and Performance Indicators

Analytics answers the question: is the project on track in terms of schedule and finances? It is available from the 360 View sidebar, the tree view in the project list, and the PMO Dashboard.

Where to View Analytics​

LocationScope
360 View ← AnalyticsA real-time view of one project
Project List ← Tree ViewA project or group, depending on the grouping
PMO ← DashboardAn overview that can be filtered by one project or all projects

What the Project Cards Show​

Financial Performance​

  • Net value
  • Budget
  • Recognized revenue
  • Unrecognized revenue

Schedule and Cost Indicators​

IndicatorSimplified Interpretation
SPI Schedule Performance IndexGreater than 1 = ahead of plan; less than 1 = behind plan
CPI Cost Performance IndexGreater than 1 = costing less than planned; less than 1 = over budget
CostCompares planned, actual, and remaining costs

Charts track changes over time so you do not rely only on an end-of-month snapshot.

The dashboard also adds progress and trends at a broader level, with a refresh button and the option to select a specific project or all projects.

How to Read the Figures Accurately​

  • Low SPI + normal CPI: work is slower, but cost is under control—review resources and dependencies.
  • Low CPI + normal SPI: the schedule is on track, but the margin is being consumed—review purchase orders, overtime, and uninvoiced change requests.
  • High unrecognized revenue: delivery has occurred but does not match the recognition policy—review line items and completion percentages.
  • High uninvoiced amount with completed deliverables: the billing plan or delivery proofs are incomplete.

Access to Figures​

If your policy hides monetary amounts, schedule indicators remain visible while financial cards are hidden. This is intentional.

Best Practices​

Do not manage the project based on how the week feels

Open Analytics before the status meeting. The SPI/CPI figures are more reliable than “we are almost finished.”

Indicators are misleading without an updated schedule

If task progress is not updated weekly, the project may incorrectly appear ahead of or behind schedule.