Project Line Items
Project line items break down the project value: what will be delivered or sold, in what quantity, at what price, and with what completion percentage. Without line items, the project remains a single financial total that is difficult to invoice or measure accurately.
Location: 360 View ← Project Line Items tab
What Line Items Do
- Connect the project to products or services in the catalog
- Show quantity, amount, completion percentage, and recognized revenue percentage
- Provide the basis for sales orders, billing plans, and deliverables when needed
Fields in the List
| Field | Meaning |
|---|---|
| Product | Item or service |
| Quantity | Line-item volume |
| Amount | Line-item value |
| Completion Percentage | Progress of this line item |
| Recognized Revenue Percentage | Portion of the line-item value recognized for accounting purposes |
How to Add a Line Item
- Open the project in the 360 View
- Select the Project Line Items tab
- Add a new record
- Select the product, quantity, and values
- Save, then review the effect on the project indicators at the top of the page
If the project is organized by phases or includes materials, licenses, and labor, create a separate line item for each group so it can later be linked to the appropriate billing-plan type.
Relationship to the Rest of the Project
- Deliverables can be linked to a line item and a work item
- The Billing Plan specifies when line-item value will be collected
- The Schedule can link a work item to a financial line item so progress and cost move together
Best Practices
A single line item named “Project Execution” prevents partial billing and accurate progress measurement. At a minimum, separate materials, licenses, and labor when that matches your business model.
If a line item’s percentage remains unchanged for weeks while the team is working, analytics will report misleading progress or delay.