Schedule and Calendar
The schedule is the visual execution plan: what work will be done, in what order, by whom, and when it starts and ends. In Drixal, it has two views within the project:
- Calendar for days, meetings, and milestones
- Schedule for the Gantt chart and work breakdown structure
Location: 360 View ← Calendar or Schedule
You can also manage work items from the project’s related records.
What the Schedule Does for Your Business
- Converts project scope into assignable packages and tasks
- Shows delays against the baseline
- Links hours and actual cost to individual tasks instead of treating the project as one block
- Feeds schedule performance indicators such as SPI
Work Breakdown Structure
A work item can have one of these types:
| Type | Role |
|---|---|
| Project Workstream | Major stream, such as design, procurement, or installation |
| Work Package | Group of tasks under a workstream |
| Activity | Execution step within a package |
| Task | Daily work assigned to a person |
| Call / Meeting / Visit / Note | Quick events created from the sidebar |
| Workflow | Item linked to an approval workflow |
Each item has planning properties:
- WBS code, such as 1.2.3
- Parent item and sibling order
- Predecessors and successors (dependencies)
- Assignment to a user or group, such as a role, team, or department
- Planned effort, cost, and duration
- Planned, baseline, and actual dates
- Task size, priority, and complexity
- Whether it is a milestone, a leaf item, and eligible for time entry
Work Item Statuses
| Status | Meaning |
|---|---|
| Planned | Not started |
| In Progress | Work is underway |
| At Risk | Requires attention even if it is not yet late or is only partially delayed |
| Delayed | Has exceeded the plan |
| Completed | Closed |
How to Build the Schedule
- Open the Schedule tab
- Create workstreams first, followed by packages and tasks
- Assign each task to a person or group
- Set dates and dependencies by dragging items in the Gantt chart when needed
- Set the baseline after customer approval so you retain a comparison reference
- Update actual progress at least weekly
Quick Create in the sidebar—Task, Meeting, Visit, and similar actions—creates a work item linked to the project without leaving the 360 View.
Calendar
The Calendar View is useful for:
- Customer meetings
- Site visits
- Single-date milestones
- Reviewing the upcoming work week with the team
Best Practices
If the schedule becomes hundreds of small tasks without packages, it becomes difficult to read and manage. Use three to four levels as a practical maximum.
If you move dates every week without retaining the baseline, the schedule indicator loses its meaning. Change the baseline only after formal approval, usually through a change request.
Enable Accepts Timesheet only for execution tasks, not for the parent workstream.